Darpan 88° Construction update 20.06.2022 | Ultra-Luxury project in Siliguri *Slab Casting- Block-1: Upto 13th floor completed. Block-2: Upto 12th floor completed *Plaster Done- Block-1: Upto 8th floor completed. Block-2: Upto 6th floor completed. *Brick Work- both Block Upto 9th floor Completed. *Electrical Line Cutups- Block-1: Upto 9th floor completed. Block-2: Upto 6th floor completed. *Plumbing Lines- Block-1: Upto 6th floor completed. Block-2: Upto 6th floor completed. Damp proofing - Upto 5th floor both completed. Call: +91 80011 81000 Visit: www.darpan88.com